Connelly Constr. Corp. v. Travelers Cas. & Surety Co. of Am., 2018 U.S. Dist. LEXIS 123009 (E.D. Pa. July 24, 2018).

This post was published in the October 4, 2018 issue of eNews published by National Association of Credit Management (NACM).

The Commonwealth of Pennsylvania Department of General Services undertook a project for the construction of a new maximum security prison facility in Montgomery County, Pennsylvania.  Walsh Heery Joint Venture (“WHJV”) was the prime contractor and it retained Connelly Construction Corporation as its masonry subcontractor.

The prime contract permitted the Commonwealth to withhold retainage from WHJV until completion of the project.  Similarly, the subcontract permitted WHJV to withhold retainage from Connelly in proportion to the retainage held by the Commonwealth.  The subcontract also included a pay-if-paid clause under which Connelly agreed that it was not entitled to payment unless, as an express condition precedent, WHJV was paid by the Commonwealth.

Completion of the project was delayed for more than two years.  As a result, the Commonwealth continued to withhold retainage from WHJV, and WHJV thus withheld more than $200,000 in retainage from Connelly, long after Connelly completed its scope of work.
Continue Reading Federal Court in Pennsylvania Holds Pay-If-Paid Clause Unenforceable Where Prime Contractor’s Inadvertent Delays Contribute to the Owner’s Withholding of Payment

NYU Hosps. Ctr. v. HRH Constr. LLC, 2015 U.S. Dist. LEXIS 31967 (S.D.N.Y. Mar. 12, 2015)

NYU Hospitals Center (“NYU”) hired HRH Construction LLC (“HRH”) to renovate NYU’s radiology center. HRH entered into subcontracts with various trades to complete the work. The renovation project was to proceed in several phases, and the contract between NYU and HRH called for HRH to submit monthly payment requisitions for costs and expenses incurred during the preceding month.Continue Reading US District Court in New York Holds Owner’s Interference Bars Claim that Contractor Breached By Abandoning Project