AWI Sec. & Investigations, Inc. v. Whitestone Constr. Corp., 2018 N.Y. App. Div. LEXIS 5867 (August 23, 2018)

A subcontractor, AWI Security and Investigations, Inc. (“AWI”), sued a general contractor, Whitestone Construction Corp. (“Whitestone”), for unpaid contract payments for providing security services on four separate construction projects.  A separate prevailing wage action (“Wage Action”) was also filed by AWI employees who worked on the projects, against both AWI and Whitestone.  Whitestone notified AWI that it was invoking the subcontract indemnity provision to withhold funds from AWI pending the outcome of the Wage Action.

Whitestone moved to dismiss AWI’s suit for payment based on a contractual limitations period requiring the suit to be brought within 6 months of: the cause of action accruing; the termination or conclusion of the contract; or the last day AWI performed work at the site, which Whitestone alleged had all occurred.  The court granted Whitestone’s motion to dismiss, finding that AWI had completed its work more than six months prior to filing its lawsuit and that AWI’s suit was barred by the contractual limitations period.  AWI appealed.
Continue Reading New York Appellate Division Holds That Contractor’s Assertion That No Payments Were Due to Subcontractor Until a Separate Prevailing Wage Action Was Resolved Precludes Application of Contractual Limitations Period

Allied World Specialty Ins. Co. v. Abat Lerew Constr., 2017 U.S. Dist. LEXIS 61794 (D. Neb. Apr. 24, 2017)

 Abat Lerew Construction (“ALC”) entered into multiple construction projects which required it to obtain surety bonds guaranteeing its performance. ALC obtained the bonds from Allied World Specialty Insurance Company (“Allied”) and also entered into an indemnity agreement with Allied.  In that agreement ALC agreed to indemnify and hold Allied harmless from and against all liability and to deposit with Allied collateral in an amount determined by Allied to be sufficient to cover liability for any claims under the bonds.

During ALC’s performance of the bonded contracts, Allied received claims on the bonds in excess of $300,000. Invoking the terms of its indemnity agreement with ALC, Allied demanded that ALC post collateral security in the amount of $400,000 to cover liability for the claims.  ALC refused and Allied commenced an action seeking equitable relief requiring ALC to deposit the demanded collateral security.  Upon commencement of the litigation, Allied asked the court to issue a preliminary injunction requiring ALC to post the $400,000 security and restraining ALC from transferring assets.Continue Reading Federal Court in Nebraska Denies Surety’s Request for Preliminary Injunction Requiring Principal to Post Collateral Security, Finding No Irreparable Harm Absent Proof That Principal Was Insolvent or Secreting Assets

Hensel Phelps Constr. Co. v. Thompson Masonry Contractor, Inc., et. al., No. 151780, 2016 Va. LEXIS 166 (Va. Nov. 3, 2016)

The dispute arose from the construction of a student health and fitness center at Virginia Tech. The prime contractor, Hensel Phelps, and its subcontractors substantially completed their work in 1998, and Virginia Tech made final payment in 1999. In April 2012, Virginia Tech discovered defects in the work, elected to repair them, and then sought to recover the costs from Hensel Phelps. Despite the significant passage of time between completion of the work and Virginia Tech’s assertion of its claims, Hensel Phelps could not invoke the statute of limitations because under Virginia Code § 8.01-231, statutes of limitation do not apply to claims asserted by Commonwealth agencies such as Virginia Tech.  Ultimately, Hensel Phelps paid $3,000,000 to Virginia Tech to settle the defective work claims.

Hensel Phelps, in turn, sought to recover from the subcontractors that performed the defective work. When the subcontractors refused to pay, Hensel Phelps commenced an action alleging, among other things, breach of contract against the subcontractors and their sureties. All of the defendants argued that Hensel Phelps’ claims were barred by the applicable statute of limitations. The lower courts agreed. On appeal, the Virginia Supreme Court affirmed.Continue Reading Virginia Supreme Court Holds That Subcontractors Did Not Waive Statute of Limitations, With The Result That The General Contractor Was Liable To Owner For Defective Work But With No Recourse Against Subcontractors Who Performed The Work