City of Gillette v. Hladky Construction, Inc.
2008 Wyo. LEXIS 139 (November 14, 2008)
The Supreme Court of Wyoming upheld an award to a Contractor of more than one million dollars against an Owner for a breach of an implied covenant of good faith and fair dealing even though the Owner did not breach the contract’s express terms.
The City of Gillette (“City”) hired Hladky Construction, Inc. (“HCI”) for the remodel and expansion of City Hall. The project specifications called for the installation of precast concrete exterior panels that matched those on the existing structure. Further, there was a requirement that the plant at which the precast panels were to be manufactured be certified under the Precast/Prestressed Concrete Institute Plant Certificate Program prior to the start of their production. HCI submitted a bid that unknown to it named an precast manufacturer which had not yet received the required certification. Both the City hired architect and structural engineer were aware prior to bid acceptance that HCI’s precast manufacturer was in the process of obtaining certification, but was not yet certified. Despite knowing that HCI’s manufacturer was not certified and a contract provision requiring the architect to notify bidders of any bid objections, no City representative objected or informed HCI about its uncertified precast manufacturer.

Somerset Village Townhomes Condominium Owners’ Association v. Allied Construction, Inc.
2008 Wash App. LEXIS 2178 (September 2, 2008)
Developer, Far Northwest Development Co, LLC (“Far Northwest”) contracted with Steinvall Construction (“Steinvall”) for the construction of the Somerset Village Townhomes. The contract between Far Northwest and Steinvall stated that “[t]he Contract Documents shall not be construed to create a contractual relationship of any kind . . . between the Owner and a Subcontractor . . .” Steinvall subcontracted portions of its work. The subcontracts incorporated the general conditions of the Far Northwest –Steinvall contract and also imposed certain obligations on the subcontractors concerning Far Northwest, including, inter alia, obtaining insurance to protect its interests and indemnifying Far Northwest for certain claims.

Lanier at McEver, L.P. v. Planners and Engineers Collaborative, Inc.
2008 Ga. LEXIS 553 (Ga. June 30, 2008)
In this case, the Supreme Court of Georgia reversed a Court of Appeals’ decision, previously reported here, holding that a provision limiting an owner/developer’s damages against the project engineer to the fees paid for the engineer’s services was void and unenforceable as against public policy.
Lanier was the owner/developer of an apartment complex. Lanier hired the defendant engineering firm, PEC, to design various aspects of the apartment complex, including the storm sewer and sanitary drainage system. The engineering agreement contained a provision stating that the total aggregate liability of PEC and its subconsultants to Lanier “for any and all claims … shall not exceed PEC’s total fee for services rendered on this Project.” The clause applied not only to liability to Lanier, but also to “all construction contractors and subcontractors on the project or any third parties.” Following construction of the Project according to the plans and specifications prepared by PEC, problems arose with the storm water system that required modification and repair by the owner. As a result, Lanier sued PEC for negligent design, breach of express contractual warranty and litigation expenses.

Bryan’s Quality Plus, LLC v. Shaffer Builders, Inc.
2008 U.S. Dist. LEXIS 61713 (E.D. Pa. Aug. 12, 2008)
The District Court for the Eastern District of Pennsylvania was faced with a motion to dismiss a defendant’s counterclaims for fraud and negligent misrepresentation. The case arose out of a subcontract between the defendant contractor and the plaintiff subcontractor in which the subcontractor agreed to complete piling work for a commercial project undertaken by defendant (the “Project”). The contractor alleged in its counterclaim that the subcontractor represented that it would complete the work in seven days, that it could install in excess of fifty piles a day, that its performance and equipment would surpass conventional methods, that it would furnish and install pile tension brackets and fasteners, and that it had sufficient credit to purchase the materials necessary to complete the work. The parties executed a written contract, although some of the work was completed prior to execution of the subcontract.

Waynesborough Country Club of Chester County v. Diedrich Niles Bolton Architects, Inc.
2008 U.S. Dist. LEXIS 45980 (E.D. Pa. July 21, 2008)
The case arose out of the design and construction of a new clubhouse for Waynesborough. Diedrich Niles Bolton Architects (“DNB”) provided professional architectural services to Waynesborough for the project and Ehret Construction served as the project’s general contractor and construction manager. Structural problems arose after the clubhouse was complete, and Waynesborough sued DNB alleging, as a result of DNB’s professional negligence and breach of contract, significant water leaks developed at various places throughout the interior of the clubhouse. DNB joined Ehret as a third party defendant. Ehret, in turn, filed a counterclaim against DNB for negligent misrepresentation, claiming that DNB’s architectural work was deficient and that Ehret’s work was delayed, disrupted and inefficient as a result of having relied upon inaccurate drawings and other architectural documents supplied by DNB during construction.

Chrysler Realty Company, LLC v. Design Forum Architects, Inc.
2008 U.S. Dist. LEXIS 42721, No. 06-CV-11785 (E.D. Mich. May 30, 2008)
The United States District Court for the Eastern District of Michigan was asked to consider whether a plaintiff’s claim for professional liability against a design professional should be dismissed where plaintiffs allowed evidence to be destroyed. Finding that the plaintiff’s intentional removal and destruction of the allegedly defective HVAC system without notice to the defendant deprived the defendant of an opportunity to develop defenses to the claims, the Court dismissed the plaintiff’s claims.

Acme Contracting, Ltd. v. TolTest, Inc
2008 U.S. Dist. LEXIS 36355 (E.D. Mich. May 5, 2008)
The United States District Court for the Eastern District of Michigan recently had to interpret an Ohio statute (O.R.C. §4113.62) which statute dealt with the enforceability of no damages for delay provisions in construction contracts. Relying on prior cases interpreting the applicable statute, the District Court found that the subcontract which limited delay claims to a time extension only was prohibited under the statute and, therefore, void and unenforceable. Although the District Court permitted the subcontractor to recover delay damages, it also concluded that the subcontractor had not proven that it was entitled to extended home office overhead costs using the Eichleay formula and refused to award such damages.

Mostellar Mansion, LLC v. Mactec Engineering & Consulting of Georgia, Inc.
2008 N.C. App. LEXIS 1011 (May 20, 2008)
Mostellar Mansion, LLC (Mansion) entered into a contract with Mactec Engineering and Consulting of Georgia, Inc. (Mactec) in connection with Mostellar’s plan to purchase a tract of land for the construction of an apartment complex (the Project Site). Under the contract, Mactec was to assess the subsurface conditions of the Project Site, determine if the Project Site was suitable for the proposed construction and provide recommendations for foundation design and site preparation for the proposed structures. The contract contained the following pertinent provisions:

Sloan Constr. Co. v. Southco Grassing, Inc.
2008 S.C. LEXIS 99 (S.C. Mar. 24, 2008)
The South Carolina Department of Transportation (SCDOT) contracted with general contractor Southco Grassing, Inc. in connection with state highway maintenance project and, in accordance with the applicable statutory bond requirements, Southco provided a payment bond for the benefit of its subcontractors and suppliers in the full contract amount. Subsequently, Southco entered into a subcontract with subcontractor Sloan to perform asphalt paving work. In June 2001, before the paving work was completed, Southco’s payment bond was cancelled when the bond’s issuer became insolvent. Notice of the insolvency and cancellation was provided to SCDOT and SCDOT requested in writing that the Southco provide a replacement bond within seven days. Southco did not reply. In the meantime, Sloan completed its work, but in January 2002 notified SCDOT that it still had not received payment from Southco for its subcontract valued at approximately $52,000 and that the payment bond had never been replaced. In March 2003, despite that it had not made full payment to Sloan, Southco advised SCDOT that it had made all payments on the project, and SCDOT released final retainage to Southco.

Atlantic City Associates LLC v. Carter & Burgess Consultants, Inc.
2008 U.S. Dist. LEXIS 25144 (D.N.J. Mar. 27, 2008)
The United States District Court for the District of New Jersey recently had to decide whether it was proper for a general contractor to set off potential claims on a private project against amounts owed to the same subcontractor on a public project. Relying upon the New Jersey Public Works Bond Act and New Jersey Trust Fund Act, the District Court concluded that it was improper for the general contractor to set off the amounts because a contractual setoff provision was insufficient to rise to the level of a waiver of the subcontractor’s rights under the Acts.