ACE Constructors, Inc. v. U.S.
2007 U.S. App. Lexis 22309 (Fed. Cir. September 19, 2007)
The US Court of Appeals for the Federal Circuit upheld a contractor’s claim for additional compensation due to differing site conditions.
ACE Constructors, Inc. (“Contractor”) entered into a contract with the United States Army Corps of Engineers (“Government”) to build a structure designated as the Ammo Hot-Load Facility, at Biggs Army Airfield at Fort Bliss in El Paso, Texas. The project included construction of a loading area for cargo planes, various roadways, buildings, a storage pad, a loading apron, and a taxiway for airplanes. The site contained hills and other terrain that needed to be excavated, leveled, and filled. The bid solicitation materials included architectural drawings and engineering specifications prepared for the government by the engineering firm of Crawford, Murphy & Tilly, Inc., which plans were incorporated into the contract.