Inc. v. Safeco Insurance Co. of America

Lexicon, Inc. v. Safeco Insurance Co. of America
No. 04-6086, 2006 U.S. App. LEXIS 3113 (6th Cir. Feb. 9, 2006)
Icon, Inc. served as a subcontractor on a steel plant expansion project in Kentucky. Pursuant to its subcontract, Icon secured a payment bond, with Safeco Insurance Company of America as surety. Lexicon, Inc. performed work on the project as a subcontractor to Icon. Lexicon incurred additional costs on the project as a result of delays for which it was not at fault. Lexicon brought a claim for these “delay and impact” costs against Safeco, as surety for Icon.