Cleveland Construction, Inc. v. Kent State University
2010 Ohio 2906, 2010 Ohio App. LEXIS 2407 (Ohio Ct. App. June 24, 2010)
The Ohio Court of Appeals held that a contractor’s failure to submit claims in accordance with the contract’s dispute process and its failure to exhaust administrative remedies prescribed by statute would bar its claims regardless of assertions as to the futility or unfairness of such procedures.