Inc. and Foster Wheeler Environmental Corporation

URS Group, Inc. v. Tetra Tech FW, Inc. and Foster Wheeler Environmental Corporation
2008 Colo. App. LEXIS 159 (February 7, 2008)
The Court of Appeal of Colorado held that the plaintiff subcontractor did not assume the risk of differing site conditions and thus its claims for differing site conditions and mutual mistake were viable. Moreover, the Court held that the economic loss rule did not bar plaintiff’s negligent misrepresentation claim, because the alleged misrepresentation occurred during negotiations before the contract was formed.