Genesee/Wyoming YMCA v. Bovis Lend Lease LMB, Inc
2012 N.Y. App. Div. LEXIS 6358(N.Y. App. Div. Sept. 28, 2012)

The Genesee/Wyoming YMCA (“YMCA”) contracted with Bovis Lend Lease LMB, Inc. (“Bovis”) and Thomas Associates Architects & Engineers (“Thomas”) for the construction of a new swimming complex. Bovis was the construction manager for the project, and Thomas was the architect. Shortly after the project was completed, defects were discovered in the roof and insulation system. An inspection indicated that the roof and insulation system were defectively designed and that improper materials had been selected.