J.P. Altmayer v. R.W. Johnson,
79 F.3d 1129 (Fed. Cir. 1996).
GSA had planned to order the carpet and trim for the office by August 1992 but did not do so despite repeated requests from Altmayer who tried to impress the importance of this for the contract to be completed