Window Specialists, Inc. v. Forney Enterprises, Inc.,
2014 U.S. Dist. LEXIS 2014 U.S. Dist. LEXIS 34702 (D.D.C. March 18, 2014)

This dispute arises out of a construction contract to repair property at Fort McNair in Washington, D.C.  The Army contracted with a general contractor, IIU Consulting Institute, who in turn contracted with defendant subcontractor, Forney Enterprises.  Forney entered into a sub-subcontract with plaintiff Window Specialists, Inc. for the labor and materials to supply and install over 680 windows and over 60 doors on the project.  During the course of the project, the Army issued a 10-day cure notice identifying numerous issues with the general contractor’s demolition of existing windows and Window Specialists’ installation of new windows.  Ultimately, Forney terminated the contract with Window Specialists and the general contractor had to demolish, re-order, and re-install all of Window Specialists’ work on the project.
Window Specialists filed suit against Forney, the general contractor, the general contractor’s payment bond surety, and the Secretary of the Army, bringing claims for breach of contract, unjust enrichment, a payment bond claim, and for injunctive relief.  Forney filed two counterclaims against Window Specialists, one for breach of contract and one seeking indemnification related to the costs the general contractor incurred replacing Window Specialists’ work.Continue Reading Federal District Court for DC Rejects Subcontractor’s Pass-Through of General Contractor’s Claim to Sub-Subcontractor