Fidelity and Deposit Company of Maryland

IES Commercial, Inc. v. Manhattan Torcon, A Joint Venture, 2018 U.S. Dist. LEXIS 164973 (D. Md. Sept. 26, 2018)

In 2009, the Army Corps of Engineers hired Manhattan Torcon Joint Venture (“MT”) as general contractor to build a biological research facility at Fort Detrick, Maryland.  MT subcontracted with IES Commercial, Inc. (“IES”) to perform the electrical system work.

In August 2013, after IES had completed over 90% of its work, a fire destroyed or damaged more than half of the facility, including significant portions of IES’s work. MT ordered IES to perform significant fire remediation work in addition to the remainder of its base contract work. In November 2013, IES and MT entered into a subcontract amendment referred to as the “Fire Rider,” which included an agreed rate schedule for the fire remediation work, along with a procedure by which IES would perform work at MT’s direction, submit daily work tickets and monthly invoices, and be paid within ten days after MT received payment from its insurer.
Continue Reading A Fire Destroying More Than Half of the Project Is Not a Cardinal Change Where the Parties Entered into a Separate Agreement to Cover the Fire Remediation Work

Fid. & Deposit Co. of Md. v. T

ravelers Cas. & Sur. Co. of Am., 2018 U.S. Dist. LEXIS 162265 (D. Nev., September 21, 2018)
Clark County School District (“CCSD”) hired Big Town Mechanical (“Big Town”) as general contractor to perform HVAC upgrades at five schools.  Big Town in turn hired F.A.S.T. Systems (“FAST”) to complete low-voltage work at the schools.  Big Town obtained performance bonds from Travelers Casualty and Surety Company of America (“Travelers”) and FAST obtained performance bonds from Fidelity & Deposit Company of Maryland (“F&D”).

Following FAST’s default on its subcontracts, F&D opted to complete FAST’s work and hired a substitute subcontractor, Perini.  In May 2012, Perini notified Big Town that it had “substantially completed” all of FAST’s work.  After Big Town refused payment, F&D filed suit against Big Town and Travelers in early 2013.  In May of 2013, CCSD rejected Big Town’s final payment application, stating that the project was incomplete and claiming there were significant defects in the work.  CCSD then sued Travelers seeking specific performance and liquidated damages for delay.  Travelers eventually settled CCSD’s suit but through its counterclaim sought reimbursement from F&D for its settlement plus costs expended to complete the project.
Continue Reading Concurrent Delay: Surety—Standing in the Shoes of Subcontractor—Is Barred From Asserting Defense of Concurrent Delay Because Subcontractor Failed to Seek a Time Extension as Required by the Subcontracts

Connelly Constr. Corp. v. Travelers Cas. & Surety Co. of Am., 2018 U.S. Dist. LEXIS 123009 (E.D. Pa. July 24, 2018).

This post was published in the October 4, 2018 issue of eNews published by National Association of Credit Management (NACM).

The Commonwealth of Pennsylvania Department of General Services undertook a project for the construction of a new maximum security prison facility in Montgomery County, Pennsylvania.  Walsh Heery Joint Venture (“WHJV”) was the prime contractor and it retained Connelly Construction Corporation as its masonry subcontractor.

The prime contract permitted the Commonwealth to withhold retainage from WHJV until completion of the project.  Similarly, the subcontract permitted WHJV to withhold retainage from Connelly in proportion to the retainage held by the Commonwealth.  The subcontract also included a pay-if-paid clause under which Connelly agreed that it was not entitled to payment unless, as an express condition precedent, WHJV was paid by the Commonwealth.

Completion of the project was delayed for more than two years.  As a result, the Commonwealth continued to withhold retainage from WHJV, and WHJV thus withheld more than $200,000 in retainage from Connelly, long after Connelly completed its scope of work.
Continue Reading Federal Court in Pennsylvania Holds Pay-If-Paid Clause Unenforceable Where Prime Contractor’s Inadvertent Delays Contribute to the Owner’s Withholding of Payment