Dooley & Mack Constructors, Inc., v. Developers Surety & Indemnity Company
2007 Fla. App. LEXIS 17769 (Fla. Ct. App. Nov. 7, 2007)
Dooley & Mack Constructors, Inc. (“Contractor”), the general contractor on a Miami-Dade Community College project, was the obligee on a performance bond issued by Developers Surety and Indemnity Company (“Surety”), on behalf of Buildtec Construction Group, Inc., the masonry subcontractor (“Subcontractor”). After Subcontractor defaulted by abandoning the job, Contractor completed the masonry work itself and sued the Surety for the resulting damages.Continue Reading Florida Court Holds Notice of Default to Surety Not Required Where Subcontract Provision as to Rights on Default Was Incorporated in Bond