Olympus Corp. v. United States,
98 F.3d 1314, 1996 U.S. App. LEXIS 27509 (U.S. Fed. Cir., Oct. 23, 1996)
Standard “Differing Site Conditions” clause in Government contract requires, as a condition to recovery under that clause, that the alleged differing condition which serves as the basis of the claim must have existed at the time the contract was executed.Continue Reading Federal Circuit Court of Appeals Denies Contractor Recovery Because Alleged "Differing Site Condition" Did Not Exist at Time of Contract Award.