Daniel Marr & Son Co. v. Coreslab Structures

Daniel Marr & Son Co. v. Coreslab Structures, Inc. et al.
No. 03-1880, 2005 Mass. Super. LEXIS 545, (Mass. Supp. Nov. 21, 2005)
In Daniel Marr & Son Co. v. Coreslab Structures, Inc. et al., No. 03-1880, 2005 Mass. Super. LEXIS 545, (Mass. Supp. Nov. 21, 2005), plaintiff sub-subcontractor sued defendant subcontractor for various breaches of contract related to the construction and erection of precast concrete panels. The original scope of work dictated the erection of the precast panels would proceed on a floor-by-floor basis. During the project, the defendant order plaintiff to alter the erection sequence, requiring plaintiff to install the precast panels on an as-directed basis. Plaintiff subsequently asserted a claim for productivity inefficiencies related to the revised sequence and other issues. Defendant attacked Plaintiff’s damages calculations as an “unsegregated partial total cost claim.”