Ellett Constr. Co., Inc. v. United States,
93 F.3d 1537, U.S. App. LEXIS, August 26, 1996
A settlement proposal in response to a termination for the convenience of the Government is a non-routine claim subject to the jurisdiction of the courts pursuant to the Contracts Disputes Act, provided that the settlement proposal ripens into a claim after negotiations have reached an impasse.
Contract Disputes Act
Federal Claims Court Holds Contractor Required to Proceed with Disputed Corrective Work under Disputes Clause; Contractor Not Entitled to Advance Judicial Determination of Propriety of Directive under Federal Courts Administration Act of 1992
By Constructlaw on
Posted in Construction Dispute
Valley View Enterprises, Inc. v. United States,
35 Fed. Cl. 378 (1996).
On September 22,1992, the Department of the Army awarded plaintiff Valley View Enterprises, Inc. (“Valley View”) a contract to replace seventeen steam lines located at the United States Military Academy in West Point, New York in connection with…