Rai Indus. Fabricators, LLC v. Fed. Ins. Co., 2018 U.S. Dist. LEXIS 74612 (N.D. Cal., May 2, 2018)
Sauer Incorporated (“Sauer”) contracted with the U.S. Army to design and construct the Operational Readiness Training Complex at Fort Hunter, California. Sauer subcontracted with Agate Steel, Inc. (“Agate”) for the erection of steel for the project. Agate’s subcontract with Sauer contained a no-damage-for-delay clause, which generally provided that extensions of time were Agate’s sole remedy for delay.
According to Agate, the project suffered from substantial delays because of the acts and omissions of Sauer. In particular, Agate alleged that Sauer failed to properly coordinate the work of its subcontractors, failed to follow the project’s schedules, failed to follow the subcontract’s change order procedures, and made unanticipated changes to the project’s scope and work flow sequence. Agate argued that these delays constituted a cardinal change and/or abandonment of the subcontract, which rendered the no-damage-for-delay clause unenforceable. Agate sued Sauer for damages from the delays and disruptions to its work.