Holloway Constr. Co. v. Department of Transportation
218 Ga. App. 243, 461 S.E. 2d 257, 1995 Ga. App. LEXIS 693 (July 13, 1995).
One of several multiple prime contractors was not entitled to sue owner for delays attributable to other prime contractor — on theory of breach of implied or express obligation — in light of clear contractual provision stating that owner would not be liable for delays attributable to contractors. Contractor barred from pursuing claim for extended overhead and equipment costs allegedly attributable to owner-directed changes in the work and owner’s failure to make prompt decisions because contractor did not provide timely request for an extension of time in accordance with contract.