Harbor Court Assoc. v. Leo A. Daly Co.,
179 F.3d 147 (4th Cir. 1999)
The plaintiffs, Harbor Court Associates and Murdock Development Company (“HCA/Murdock”) were the developers of Harbor Court Complex, located in the Inner Harbor area of Baltimore, Maryland. On April 28, 1983, HCA/Murdock hired Leo Daly (“Daly”), an architect with a principal place of business is in Nebraska, to design and construct the project. The parties used an A.I.A. document, which stated that, for disputes arising out of the contract: “any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the relevant Date of Substantial Completion of the Work, and [as to any failures occurring after substantial completion] not later than the date of issuance of the Final Certificate of Payment.”
breach of contract
The Supreme Court of California holds that an obligee may not recover in tort for a surety’s breach of covenant of good faith and fair dealing implied in a performance bond.
Cates Constr., Inc. v. Talbot Partners et al.,
1999 Cal. LEXIS 4847 (Co. July 29, 1999)
In 1989, defendant Talbot Partners (“Talbot”) hired plaintiff Cates Construction, Inc. (“Cates”) to build a condominium project in Malibu, California. The construction contract required Cates to have the project ready for occupancy in eight months. The contract also required Cates to furnish a performance bond and a labor and materials bond, both of which were subsequently issued by Transamerica Insurance Company (“Transamerica”).
Utah Supreme Court considers non-contractual liability of contractors for damages resulting from defective work
Interwest Construction v. A.H. Palmer & Sons,
292 Utah Adv. Rep. 27, 1996 Utah LEXIS 44 (Utah June 14, 1996)
The Supreme Court of Utah held that the intermediate court of appeals erred in holding that a tort action for negligence and strict liability arising out of a breach of contractually defined obligations was precluded. However, the Supreme Court of Utah also held that the tort claims should be dismissed because the claimant failed to prove causation between the alleged defect and the resultant injury.
New York Court Holds General Contractor Who Delays Acceptance or Seeks to Negotiate Better Deal May Not Recover From a Subcontractor Who Fails to Perform Work On a Project for Which it Had Submitted a Bid
Lahr Construction Corp. (doing business as LeCesse Construction Co.) v. J. Kozel & Son, Inc.,
640 N.Y.S.2d 957 (Misc 1996).
This is an action brought by a general contractor against a subcontractor for damages where the subcontractor moved for summary judgment saying that the general contractor could not recover damages…
Minnesota Court of Appeals Holds Evidence of Contractors Profit Inadmissible in Dispute Concerning Proper Unit Price to Apply to Excavation Work Through Rock
AyrCom Contractors, Inc. v. U.S. West Communications, Inc.,
1995 Minn. App. LEXIS 981 (Minn. Ct. App. Aug. 1, 1995)
Contract which contained two unit prices for laying cable in rock was ambiguous and court admitted extrinsic evidence regarding the meaning of the ambiguous provisions. Evidence regarding the contractor’s profit or loss was not admissible because its relevance was outweighed by its substantial prejudice regarding the meaning of an ambiguous contract provision. A state’s requirement of a “certificate of authority” to conduct business in the state as a prerequisite to maintaining an action was not a requirement for subject matter jurisdiction, but rather was related to a party’s capacity to sue and, therefore, was waived if not raised timely.