Associated Mechanical Contractors, Inc. v. Martin K. Eby Constr. Co., Inc.
No. 00-10784, 2001 U.S. App. LEXIS 24235 (11th Cir. Nov. 9, 2001)
Martin K. Eby Construction Company, Inc. (“Eby”) was the prime contractor on a Georgia prison construction project. Eby entered into subcontract with Associated Mechanical Contractors, Inc. (“Associated”) pursuant to which Associated agreed to perform the mechanical, heating, ventilation, air-conditioning, and plumbing work for the project.