Gainesville Mech., Inc. v. Air Data, Inc., No. A19A0518., 2019 BL 229069 (Ga. Ct. App. June 19, 2019)

The First Division of the Georgia Court of Appeals affirmed a superior court’s decision to confirm an arbitration award against Appellant Gainesville Mechanical, Inc. (“Gainesville”) because Gainesville failed to show that the arbitrator manifestly disregarded the law governing the “modified total cost” approach to damages.

Continue Reading Georgia Court of Appeals Affirms Superior Court’s Confirmation of Arbitration Award, Finding That Arbitrator Did Not Manifestly Disregard Law Governing the “Modified Total Cost” Approach to Damages

Aspic Eng’g & Constr. Co. v. ECC Centcom Constructors LLC, No. 17-16510, 2019 BL 26363 (9th Cir. Jan. 28, 2019)

Aspic Engineering and Construction Company (“Aspic”), a local Afghan subcontractor, entered into multiple subcontracts with ECC Centcom Constructors and ECC International (“ECC”), the prime contractor, to construct buildings and facilities in Afghanistan.  The subcontracts contained terms and conditions “applicable to all U.S. Government subcontracts,” and mandated that Aspic owed ECC the same obligations that ECC owed to the federal government.  The subcontracts also incorporated multiple Federal Acquisition Regulation (“FAR”) clauses, including FAR 49.2 through 49.6, which govern the recovery of expenses in the event a contractor is terminated for convenience, i.e. required documentation and procedures.

Continue Reading Ninth Circuit Finds Arbitration Award Is ‘Irrational’ Because It Disregards the Contract’s Plain Text Simply to Reach a Just Result