Servidone, Inc./B. Anthony Constr. Corp., J.V. v. State of New York, No. 2016-05238, 2019 BL 7232 (App. Div., 2d Dept. Jan. 09, 2019)

Servidone, Inc./B. Anthony Construction Corp., J.V. (the “Contractor”) and the New York State Department of Transportation (the “DOT”) entered into a construction contract to reconstruct and replace bridges on Route 59 in New York State. The Contractor retained L.M. Sessler Excavating & Wrecking, Inc. (the “Subcontractor”) to perform the demolition and disposal portion of the project.

SWN Prod. Co., LLC v. Long, 2017 W. Va. LEXIS 892 (W. Va. Oct. 18, 2017)

Respondents Richard and Mary Long (“Respondents” or “Lessors”) brought a state court action against Petitioner SWN Production Company, LLC (“Petitioner” or “Lessee”) seeking to recover alleged payments owed pursuant to an oil and gas lease (the “Lease”) entered into between Petitioner and Respondent.
Petitioner filed a motion to compel arbitration, relying on the Lease’s arbitration provision, which reads:  “In the event of a disagreement between Lessor and Lessee concerning this Lease, performance thereunder, or damages caused by Lessee’s operations, the resolution of all such disputes shall be determined by arbitration in accordance with the rules of the American Arbitration Association.”