Allgood Electric Co. v. Martin K. Eby Constr. Co.

Allgood Electric Co. v. Martin K. Eby Constr. Co.,
85 F.3d 1547, 1996 U.S. App. LEXIS 15252 (11th Cir. June 25, 1996)
Under Georgia law, subcontractor’s release of all claims against property on which project was located did not operate to release claims against contractor, nor was contractor entitled to benefit of release in which contractor was not mentioned by name.
Plaintiff Allgood Electric Company (“Allgood”) was the electrical subcontractor on a prison project for the Georgia Building Authority (“GBA”). Defendant Martin K. Eby Construction Company, Inc. (“Eby”) was the general contractor. Allgood sought to recover increased costs allegedly caused by Eby’s failure to coordinate various aspects of the project. Allgood also claimed entitlement to retainage.