Int’l Fidelity Ins. Co. v. Americaribe-Moriarty JV, 2017 U.S. App. LEXIS 3628 (11th Cir. Feb. 28, 2017)

Americaribe-Moriarty Joint Venture (“Americaribe”) entered into a subcontract with Certified Pool Mechanics I, Inc. (“CPM”) for construction of a pool in a mixed-use development that Americaribe was building in Miami, Florida. CPM provided a performance bond, issued by International Fidelity Insurance Company and Allegheny Casualty Company (collectively, “Fidelity”) as security for performance of the pool subcontract.  According to Americaribe, CPM failed to perform its obligations under the pool subcontract.  As a result, Americaribe terminated CPM, made a claim on the performance bond, and contemporaneously hired a replacement contractor (“Dillon”) to complete CPM’s scope of work.

In the event of default by CPM, the subcontract required three days’ written notice before undertaking completion of CPM’s work. The bond incorporated the subcontract by reference and also required a further, but undefined, period of time after CPM’s termination during which Fidelity could evaluate options for responding to CPM’s alleged default.  In the event that Fidelity did not conduct such an evaluation with reasonable promptness, Americaribe could declare a default by Fidelity upon seven days’ written notice.  Although Americaribe provided the written notices of default, it proceeded to complete CPM’s work with Dillon before the notice periods expired.