James Corp. v. North Allegheny School District
No. 1268 C.D., 2007 Pa. Commw. LEXIS 636 (Pa. Commw. Ct. Nov. 30, 2007)
The Pennsylvania Commonwealth Court held that the “measured mile” method of proving damages for an acceleration claim was legally sufficient to establish the extent of the contractor’s damages. The Court also held the contractor’s failure to provide notice in accordance with the contract was not fatal to the claim, and that attorney fees and expenses under the Prompt Payment Act must be apportioned to those fees and expenses associated with recovering payment’s due under the contract.Continue Reading Pennsylvania Commonwealth Court Holds Written Notice of Claim Requirement Excused and Accepts “Measured Mile” Method of Proving Inefficiency Damages