Fraser Eng’g Co. v. IPS-Integrated Project Servs., LLC, 2018 US Dist. LEXIS 51392 (D.N.H. March 27, 2018)

IPS-Integrated Project Services, LLC (“IPS”) was the general contractor on a project to design and construct a manufacturing facility in Portsmouth, New Hampshire. IPS subcontracted with Fraser Engineering Company (“Fraser”) for the project’s mechanical and plumbing scope of work. Shortly after award, IPS notified Fraser that it may be directed to accelerate its work. In response, Fraser put IPS on notice that acceleration would result in labor inefficiencies for which it expected to be reimbursed.  Thereafter, IPS directed Fraser to accelerate and Fraser complied by using extra overtime over the next several months. During that time, the parties communicated numerous times about Fraser’s claim for labor inefficiencies.

Under its subcontract with IPS, Fraser was required to submit lien waivers with each of its payment applications. According to the court, the waivers at issue “do not merely release lien rights, but also ‘all claims, demands, or causes of action . . . which [Fraser] has, or might under any present or future law, assert against [IPS] or [the owner] relating to the Partial Payment and/or the labor services, materials or equipment for which the partial payment has been made.’” During its work, Fraser submitted eight such waivers.

Central Ceilings, Inc. v. Suffolk Constr. Co., Inc., 2017 Mass App. Lexis 36 (March 29, 2017)

 The Massachusetts State College Building Authority contracted with Suffolk Construction Company (“Suffolk”) to serve as the general contractor for the construction of dormitories at Westfield State University (“the Project”). Suffolk subcontracted with Central Ceilings, Inc. (“Central”) to install interior and exterior framing, drywall, and door frames for the Project.

Central’s work was impeded by Suffolk’s failure to: coordinate the work of other trades; establish proper elevation, column, and control lines; timely and properly coordinate delivery of the door frames; and ensure that the buildings were weather-tight and properly heated. Its workers were forced to repeatedly demobilize from one area and remobilize in another, and to work in the same space and at the same time as other subcontractors, i.e. stacking of trades.  Central’s project manager and other supervisors were forced to coordinate and administrate the remobilizations.  Both the remobilizations and the stacking of trades significantly increased Central’s labor costs.