Circle Y Construction, Inc. v. WRH Realty Services, Inc.
2010 U.S. Dist. LEXIS 67812 (N.D. Ga. July 8, 2010)

Circle Y Construction, Inc. contracted with WRH Hidden Colony to perform certain renovation work at nine unoccupied apartment units. The contract designated Brown, vice president of construction services for WRH Realty Services, as the person responsible for administering the contract on behalf of WRH Hidden Colony and stated that Brown was the only person authorized to approve changes to the scope of work. The contract further provided that “all extra or changed work shall be authorized by a written change order.”

Kuhn Construction Company v. Ocean and Coastal Consultants, Inc.
2010 U.S. Dist. LEXIS 71057 (D. Del. July 15, 2010)

Diamond State Port Corporation (“DSPC”) engaged Ocean and Costal Consultants, Inc. (“OCC”) to prepare engineered drawings, plans, and specifications for a project at the Port of Wilmington in Delaware. In soliciting bids, DSPC utilized the bid documents designed and prepared by OCC. Kuhn Construction Company (“Kuhn”) relied upon those documents to prepare its bid for work on the project. As the lowest bidder, Kuhn entered into a contract with DSPC.

Raito, Inc. v. Cardi Corp.
2010 R.I. Super. LEXIS 108 (RI Super. Ct. July 14, 2010)

The Superior Court of Rhode Island was recently asked to reconsider its earlier ruling in which it found that a condition precedent to recovery under a performance bond was not satisfied and, therefore, summary judgment in favor of the surety was warranted. The Court found no reason to disturb its prior ruling and denied the motion for reconsideration.

John L. Mattingly Constr. Co. v. Hartford Underwriters Ins. Co.
2010 Md. LEXIS 327 (Md. July 27, 2010)

The Maryland Court of Appeals determined that the waivers of subrogation clause in AIA A107-1997 is ambiguous as to whether it encompasses losses sustained after completion of construction and final payment. As a result, the case was remanded to the Court of Special Appeals so that it could resolve the ambiguity by considering extrinsic evidence.

In 2002, K.B.K., Inc. and John L. Mattingly Construction Company, Inc. entered into AIA form contract number A107-1997 to build an Arby’s Restaurant. Section 16.4 of the Contract required K.B.K. to “purchase and maintain property insurance until final payment has been made” or until no person … other than K.B.K. had an insurable interest.” Section 16.5 of the Contract stated that K.B.K. and Mattingly “waived all rights against … each other and any of their subcontractors for damages covered by property insurance … applicable to the Work.”

Mastec North America, Inc. v. El Paso Field Services, L.P.
2010 Tex. App. LEXIS 3436 (Tex. App. May 6, 2010)

The Court of Appeals of Texas recently held that when a contract places the risk of differing site conditions on the contractor, the contractor is not required to bear the risk “that the bid documents misrepresent the nature and amount of the work to be performed.”

The matter involved replacement of a pipeline that extended from Houston to Corpus Christi. Defendant El Paso contracted with Plaintiff MasTec, for the replacement work.

Weigand Construction Co., Inc. v. Stephens Fabrication, Inc.
2010 Ind. App. LEXIS 1109 (Ind. Ct. App. June 25, 2010)

Ball State University (BSU) contracted with Weigand Construction Co. (“Weigand) to act as the general contractor for its Music Instruction Building project. Weigand subcontracted the structural steel work to Stephens Fabrication, Inc. (“Stephens”). Stephens was to manufacture the steel, perform certain engineering and prepare shop drawings. Stephens contracted with sub-subcontractors, Argo and Wilson, to perform the engineering and prepare the shop drawings.

Turnberry Pavillon Partners, L.P. v. M.J. Dean Construction, Inc.
2010 U.S. App. Lexis 9832 (9th Cir. May 13, 2010)

Developer built a luxury condominium tower and hired contractor to serve as both the construction manager and concrete subcontractor. A separate interior drywall and site wall subcontractor was also hired for the Project. A series of lawsuits arose. In the first lawsuit, construction manager was found liable for causing “lost production” and “uncompensated overtime” to site wall subcontractor due to its negligent concrete work as well as negligent construction management. While cross-appeals were pending on the matter Developer paid $2.1 to settle the site wall subcontractor’s claim. In a second case, condominium association sued Developer for construction defects. In turn, Developer filed a third-party complaint against construction manager as well as other subcontractors alleging that their negligence caused defects in the Project. Ultimately, the parties to the second suit reached a settlement whereby Developer and construction manager paid the condominium association $2 million and $600,000 respectively.

Village of Sturtevant v. STS Consultants, Ltd.
2010 Wisc. App. LEXIS 433 (Wis. Ct. App. June 9, 2010)

The Court of Appeals of Wisconsin recently considered whether a design professional could maintain a claim for contribution against a subcontractor on the basis that the subcontractor had a duty to advise that the design was not suited for the intended application. The Court of Appeals upheld the lower court’s dismissal of such claims on the basis that the subcontractor had no design or construction responsibility and therefore could not be a joint tortfeasor.

Harris Constr. Co., Ltd. v. GGP-Bridgeland, L.P.
2010 U.S. Dist. LEXIS 46477 (S.D. Tex. May 12, 2010)

The U.S. District Court for the Southern District of Texas determined that the issue whether the Texas Supreme Court would recognize a claim for breach of implied warranty against an owner or a design professional providing defective plans had been resolved by the Fifth Circuit in Interstate Contracting Corp. v. City of Dallas, 407 F.3d 708 (5th Cir. 2005). The Court concluded that the Texas would apply the Lonergan rule, which requires contractual language indicating an intent to shift the burden of risk of defective design to the owner or a design professional hired by the owner to make the plans and specifications.

Centex/Vestal J.V. v. Friendship West Baptist Church
2010 Tex. App. LEXIS 4346 (Tex. App. June 10, 2010)

The trial court denied a motion to confirm an arbitration award and granted a motion to vacate finding that the arbitrator exceeded his authority when he determined the validity of and awarded the general contractor damages on its pass through subcontractor claims. On appeal, the Court of Appeals reversed the trial court, holding that because of the breadth of the arbitration clause, the arbitrator was authorized to determine the pass through subcontractor claims, and entered an order confirming the arbitrator’s award.