Gables Construction, Inc. v. Red Coats, Inc., No. 23, 2020 BL 193791, 2020 MD LEXIS 264 (Md. May 26, 2020)

Upper Rock II, LLC (“Upper Rock”) contracted Gables Construction, Inc. (“GCI”) to construct a multi-building apartment complex in Rockville, Maryland (the “Project”) per the terms of the American Institute of Architects (“AIA”) A102TM-2007, Standard Form Agreement Between Owner and Contractor and AIA A201TM – 2007, General Conditions of the Contract for Construction.  The General Conditions required Upper Rock to purchase and maintain a property insurance policy.  It also contained a waiver of subrogation provision under which Upper Rock waived all rights against GCI and other Project participants for damages caused by fire to the extent covered by insurance.

The U.S. Supreme Court issued a unanimous decision on June 1 in GE Energy Power Conversion France SAS, Corp. v. Outokumpu Stainless USA, LLC, holding that, in some circumstances, even nonsignatories to an agreement may invoke international arbitration. The Court ruled that the U.N. Convention on the Recognition and Enforcement of Foreign Arbitral Awards (the New York Convention) did not prohibit the application of the U.S. doctrine of equitable estoppel to permit the enforcement of arbitration agreements by nonsignatories. In doing so, the Court clarified that the doctrine of equitable estoppel recognized under Chapter 1 of the Federal Arbitration Act (FAA) for U.S. domestic arbitrations could also be applied to international arbitration proceedings governed by Chapter 2 of the FAA.

For parties who regularly engage in multi-tiered international commercial arrangements like the kind seen in GE Energy, the ruling expands the reach of international arbitration agreements and gives those parties greater clarity into their own ability to utilize international arbitration to resolve complex disputes.

D.A. Nolt, Inc. v. The Philadelphia Municipal Authority, 2020 BL 199761 (E.D. Pa. May 28, 2020)

The Philadelphia Municipal Authority (the “Authority”) contracted D.A. Nolt, Inc. (Nolt) to renovate a building that would serve as the City’s new police headquarters. After Nolt had performed a portion of the renovation work, the Authority cancelled the project. Nolt sued the Authority, alleging that the Authority owed it $2.5 million for work performed before the project was cancelled. The Authority denied that payment was due, claiming that Nolt had delayed the project by 255 days and that a $10,000 per day liquidated damages provision in the contract thus offset Nolt’s claim.

Nolt moved for summary judgment on the Authority’s liquidated damages counterclaim. It argued that the provision was unenforceable because the $10,000 per day amount was not a reasonable forecast or approximation of the loss the Authority expected to suffer in the event of delay. Nolt cited testimony from the Project Director for the City’s Department of Public Property, who was responsible for finalizing the Authority’s contract with Nolt. The Director testified that he did not estimate the anticipated harm that might occur in the event of a delay in Nolt’s work. Rather, he determined that $10,000 per day was reasonable because prior City projects of a similar scope and magnitude included $10,000 per day liquidated damages provisions. The Director was not personally involved in the analysis which the City had undertaken on the referenced prior projects, and he did not personally analyze any of the calculations or estimates that the City completed for those prior projects.

N. Plains Res. Council v. United States Army Corps of Eng’rs, No. 4:19-cv-00044-BMM, 2020 BL 35412 (9th Cir. May 14, 2020)

Oil and gas pipeline construction may no longer proceed under Nationwide Water Permit 12 (NWP 12). The Ninth Circuit, by way of a two-judge panel, denied challenges to a district court decision vacating NWP 12 and enjoining the United States Army Corps (Army Corps) from authorizing oil and gas pipeline construction projects pursuant to NWP 12. The Order, which was issued without an opinion, has national effect and set a briefing schedule for reconsideration of a motion for an administrative stay. N. Plains Res. Council v. United States Army Corps of Eng’rs, No. 4:19-cv-00044-BMM.

On April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America,1 effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction subcontracts to the extent the subcontractor seeks recovery against a general contractor’s payment bond surety. Although the Crosno case involved a public works project, the rationale and holding should apply with equal force to private works projects. Basing the bulk of its decision on the Wm. R. Clarke Corp. v. Safeco Insurance Co.2 case, the court found that an open-ended “pay-when-paid” provision in a subcontract is not enforceable against a subcontractor that seeks to recover on a public works payment bond claim. This article discusses the Crosno decision and the implications for contractors on both sides of the contract moving forward.

Days after the World Health Organization declared the COVID-19 outbreak a global pandemic, governments from around the world scrambled to enact measures aimed at mitigating the spread of the virus. In the United States, cities and states have enacted travel restrictions, issued shelter-in-place orders, and directed nonessential businesses to shutter. While all aimed at mitigating the spread of the virus, these measures will have an immense disruptive impact on businesses and industries around the world — the construction sector included.

As notices concerning force majeure, changes in law, and change orders swirl, parties should prepare themselves for how these disputes will be managed and resolved. The COVID-19 outbreak will rapidly reshape how the construction sector does business. This article offers our insight into just once facet of the construction industry: alternative dispute resolution and how the COVID-19 outbreak has and will affect construction disputes going forward.

On April 20, Pennsylvania Gov. Tom Wolf amended his March 19, 2020 Order titled, “Regarding the Closure of All Businesses That Are Not Life Sustaining.” Under the previous order, construction was permitted to continue only if the business qualified as “life-sustaining” and was performing emergency repairs or if the business obtained a waiver.

The amended order paves the way for construction projects to start again throughout the Commonwealth. On April 23, Gov. Wolf announced that statewide construction can commence on May 1, 2020 and provided additional information related to the amended order in an accompanying document titled “Guidance for Businesses in the Construction Industry Permitted to Operate During the COVID-19 Disaster Emergency.” Gov. Wolf specified that the amended order applies to “all businesses in the construction industry in the Commonwealth, including those in new construction, renovation, and repair[.]” Prior to May 1, all construction industry businesses must continue to follow existing guidelines. A full list of businesses that may maintain in-person operations before May 1 can be found here.

Much has been written about whether and how COVID-19 qualifies as a force majeure event, and some additional information can be found here. But typical force majeure provisions entitle contractors to only schedule relief. While force majeure clauses may limit exposure to liquidated or consequential damages for delays, contractors who incur increased costs resulting from COVID-19 related delays should carefully evaluate the entirety of their contractual rights to not only an extension of time, but also recover prolongation costs. To assist in this endeavor, this article looks beyond force majeure to other potentially relevant contractual provisions. Potential remedies under the various contractual clauses discussed below will depend on the specific contractual language and project-specific facts.

As the COVID-19 pandemic continues to upend carefully choreographed arbitration schedules, parties, counsel and arbitrators have expressed interest in the use of video-conferencing technology to manage remote arbitration hearings. And while arbitration is no stranger to video conferencing, the arbitration community has never sought to utilize this technology on the scale being imagined today. As a result, counsel and arbitrators have clamored for guidance on how to effectively structure and manage remote arbitration proceedings.

This post seeks to introduce readers to the “Seoul Protocol on Video Conferencing in International Arbitration” as a potential resource. Released in March 2020, but developed long before the COVID-19 global pandemic, the Seoul Protocol offers a standard set of protocols that counsel and arbitrators may turn to for guidance on how to address some of the logistical challenges presented by remote arbitration hearings. While not directly applicable to all circumstances involving video hearings, and principally targeted at international arbitration practitioners, the Seoul Protocol offers helpful default standards that may be more widely applicable to streamline video-conference proceedings.

Some of the key features of the Seoul Protocol are summarized below.

With the signing of the United Nations Convention on International Settlement Agreements Resulting from Mediation in August 2019, there has been a newfound focus on how parties can improve and expand the use of alternative forms of dispute resolution outside conventional litigation and arbitration proceedings.  Pepper Hamilton attorneys Albert Bates