ACE Constructors, Inc. v. U.S.
2007 U.S. App. Lexis 22309 (Fed. Cir. September 19, 2007)
The US Court of Appeals for the Federal Circuit upheld a contractor’s claim for additional compensation due to differing site conditions.
ACE Constructors, Inc. (“Contractor”) entered into a contract with the United States Army Corps of Engineers (“Government”) to build a structure designated as the Ammo Hot-Load Facility, at Biggs Army Airfield at Fort Bliss in El Paso, Texas. The project included construction of a loading area for cargo planes, various roadways, buildings, a storage pad, a loading apron, and a taxiway for airplanes. The site contained hills and other terrain that needed to be excavated, leveled, and filled. The bid solicitation materials included architectural drawings and engineering specifications prepared for the government by the engineering firm of Crawford, Murphy & Tilly, Inc., which plans were incorporated into the contract.
Construction Dispute
Federal District Court in Illinois Holds “All Risk” Insurer’s Claim Against Contractor For Breach Of Contract And Negligence Defeated By A Waiver Of Subrogation With Respect To “[Insurance] Carried Or Required To Be Carried Pursuant To This Agreement” – Rejects Insurer’s Interpretation As To Scope Of Waiver As Too Restrictive – Indemnity Claim Survives
Federated Dep’t Stores, Inc. v. M.J. Clark, Inc.
2007 U.S. Dist. LEXIS 51826 (N.D. Ill. July 17, 2007)
After a flood caused by a leak in the sprinkler system during remodeling at a Bloomingdale’s store in Chicago damaged the first five floors of the store, plaintiffs, Bloomingdale’s and its owner Federated, sued defendant contractor, subcontractor, and building manager for breach of contract, negligence, and indemnification.
The agreement between the contractor and owner provided the contractor agreed to indemnify the owner. It further provided that each party waived all rights against the other for any loss or damage “for which property insurance is carried or required to be carried pursuant to [the parties’] Agreement.” Specifically excepted from the waiver were the contractor’s indemnification responsibilities. During the time of the flood, the owner was covered by an “all risk” insurance policy. Among other things, the policy excluded ordinary wear and tear and errors in design or faulty workmanship.
Federal Circuit Court of Appeals Reverses ASBCA Holding That ROICC Was Authorized to Commit Government To Compensable Contract Changes
Donald C. Winter v. CATH-DR/BALTI JOINT VENTURE
2007 U.S. App. Lexis 19565 (Fed. Cir., August 17, 2007)
The United States Court of Appeals for the Federal Circuit (“CAFC”) affirmed in part, reversed in part, and vacated and remanded in part the United States Armed Services Board of Contract Appeals (“ASBCA”) decision that CATH-dr/Balti Joint Venture (“CATH-Balti”) was entitled to an equitable adjust for contract modifications, issued by the Resident Officer in Charge of Contracts (“ROICC”), that called for work not covered under its contract with the United States Navy (“Navy”). The primary basis for reversal was the unambiguous language of the Federal Acquisition Regulation (“FAR”), e.g., 48 C.F.R. § 1.601(a) and 48 C.F.R. § 43.102, Defense Federal Acquisition Regulation Supplement (“DFARS”), 48 C.F.R. § 201.602-2, and FAR Clause 48 C.F.R. § 52.243-4 (Changes Clause), DFARS Clause 48 C.F.R. § 52. 201-7000 (Contracting Officer’s Representative), and Naval Facilities Engineering Command (“NAVFAC”), 5252.201-9300 (Contracting Officer Authority) and 5252.242-9300 (Government Representatives), which were incorporated into the contract and clearly indicated that the ROICC did not have the authority to change the scope of work or authorize compensable changes.
Fourth Circuit Court of Appeals Holds Owner’s Negligence Cause of Action Against Subcontractor Barred by the Economic Loss Rule
Dur v. Western Branch Diesel, Inc.
2007 U.S. App. LEXIS 16237 (4th Cir. July 9, 2007)
Following the precedent of the Supreme Court of Virginia in Sensenbreunner v. Rust. Orling & Neale, Architects, Inc., 374 S.E.2d 55 (Va. 1988), the Fourth Circuit Court of Appeals upheld the district court’s grant of a motion for summary judgment. The Court held that damage to an owner’s boat caused by an electrical fire fell within the scope of the contract between the owner’s general contractor and the subcontractor and amounted to nothing more than economic loss, which barred the owner from maintaining a cause of action for negligence against the subcontractor.
Massachusetts Court Holds Architect May Be Liable to Worker for Injuries Resulting From Defects in Contractor’s Work Where Architect Is Contractually Obligated to Inspect Work for Conformity With Plans and Specifications
Mellon v. Shriners Hospitals for Children
2007 Mass. Super. LEXIS 188 (Mass. Super. Ct. June 26, 2007)
The Superior Court of Massachusetts recently considered whether an architect of record on a construction project owed a duty to a third party construction worker on the project for injuries sustained as a result of improper installation of grates. To resolve this issue, the Court found that the whether a duty was owed rested on the language of the architectural services agreement at issue and the level of control the Architect exerted on the job site.
Federal District Court In West Virginia Holds Pay-If-Paid Clause No Defense To Miller Act Claim
U.S. ex. rel. Straightline Corp. v. American Casualty Corp.
2007 U.S. Dist. LEXIS 50688 (N.D. W. Va 2007)
The United States District Court for the Northern District of West Virginia held that a “pay-if-paid” clause was not a valid defense to a Miller Act claim. Straightline, involved a contract dispute…
New Jersey Court Holds Contract Clause Providing for Accrual of Statute of Limitations on Substantial Completion Cannot Be Circumvented By Application of Discovery Rule
Trinity Church v. Atkin
925 A.2d 720, 2007 N.J.Super.LEXIS195 (N,J, Super, App. Div., June 27, 2007)
Contractual clauses providing for the date of accrual on construction projects are valid in New Jersey. The Superior Court of New Jersey, Appellate Division, affirmed summary judgment in favor of defendants who allegedly performed defective renovation and construction work on a historical building because the plaintiff failed to file a timely action within the period of the statute of limitations.
PA Court Holds Incorporation of Prime Contract Indemnity Provision Into Subcontract Insufficient to Require Subcontractor To Indemnify General Contractor For Its Own Negligence
Integrated Project Services v. HMS Interiors, Inc.
2007 Pa. Super 246, 2007 Pa. Super. LEXIS 2606 (Pa. Super Ct., April 16, 2007)
This is an appeal from a decision in the lower court wherein a general contractor, “Integrated Project Services, (“General Contractor”) sued a subcontractor, HMS Interiors, Inc. (“Subcontractor”) for a declaratory judgment that the Subcontractor was obligated to indemnify the General Contractor for the General Contractor’s negligence. The Subcontractor filed a motion for judgment on the pleadings which was granted by the lower court and the General Contractor appealed that decision.
Minnesota Court Rules Architect-Client Relationship Is Not Per Se Fiduciary
Carlson v. SALA Architects, Inc.
2007 Minn. App. LEXIS 74
The of Minnesota Court of Appeals reversed entry of summary judgment in favor of a purchaser of architectural services, holding, among other things, that the relationship between an architect and its client is not per se a fiduciary relationship. Rather, the Court held that whether a fiduciary relationship exists was a question of fact which was unable to be resolved on summary judgment.
Vermont Court Reverses Award Of Consequential Damages To Owner In Construction Defect Case
EBWS, LLC v. Britly Corporation
2007 VT 37; 2007 Vt. LEXIS 69 (Vt. May 25, 2007)
The Vermont Supreme Court held that the cost of an owner’s anticipated voluntary payments of employee wages and for product purchases during the temporary shutdown of a creamery pending repair of construction defects were not recoverable consequential damages because they could not reasonably have been within the contemplation of the defendant when it contracted to build the creamery.