RSP Architects, Ltd. v. Five Star Dev. Resort Communities, LLC
306 P.3d 93 (Ariz. Ct. App. 2013)

This action arose from a payment dispute on a construction project where an architectural firm, RSP Architects, Ltd. (“RSP”), contracted with a developer, Five Star Development Resort Communities, LLC (“Five Star”), to provide architectural services for a development known as the Palmeraie (the “Project”). Pursuant to the architectural services contract (the “Architectural Agreement”), RSP was tasked with several different duties, including “construction administration,” “overall coordination,” and “conceptual design” related to the Project. For its services, RSP was to receive approximately $3,000,000. Prior to completion, however, RSP ceased work on the Project and sued Five Star, alleging, among other claims, a violation of Arizona’s Prompt Payment Act, A.R.S. § 32-1129 et seq. (the “PPA”).

Engeman Enterprises, LLC, v. Tolin Mechanical Systems Company
2013 Colo. App. LEXIS 345 (Colo. App. Mar. 14, 2013)

Engeman operates a cold storage facility and Tolin designs, installs, maintains, and repairs cooling systems. In 2008, Engeman engaged Tolin for an emergency repair at Engeman’s facility. The parties entered into two agreements, both of which stated that Tolin would perform its work in a “prudent and workmanlike manner,” and which disclaimed Tolin’s liability beyond repairing issues caused by defective workmanship.

Maisel v. Erickson Construction, Inc.
2012 U.S. Dist. LEXIS 108726 (D. Colo. August 3, 2012)

Plaintiff contracted with Charles Cunniffe & Assoc. Architects (“CCA”) for architectural services. Plaintiff separately contracted with Erickson Construction, Inc. (“Erickson”) for construction and general contractor services. No contract existed between CCA and Erickson.

Plaintiff sued both CCA and Erickson for various defects and design deficiencies, and asserted claims for breach of contract, breached of implied warranties, negligence and vicarious liability. Erickson cross-claimed against CCA for negligence, breach of contract (on a third-party beneficiary theory), indemnification and contribution.

LeBlanc v. Logan Hilton J.V.
463 Mass. 316 (2012)

The Massachusetts Supreme Court ruled where there is evidence that design professionals had actual knowledge of deficiencies in the installation of electrical switchgear but failed to fulfill their contractual duties to report the deficiencies to the property owner, the evidence of is sufficient to support a finding of professional negligence without an expert opinion.

GII Industries, Inc. v. New York Dep’t of Transp.
2011 Bankr. LEXIS 3663 (Bankr. E.D.N.Y. Sept. 30, 2011)

The Bankruptcy Court for the Eastern District of New York considered the appropriate method for calculating a contractor’s inefficiency damages and whether the contractor was entitled to prejudgment interest in connection with a highway reconstruction project. The Court held that the total cost method was the appropriate manner by which to calculate damages and that the contractor was entitled to prejudgment interest running from the date final payment was due.

SNC-Lavalin America, Inc. v. Alliant Techsystems, Inc.
2011 U.S. Dist. LEXIS 118312 (W.D. Va. Oct. 13, 2011)

SNC-Lavalin America, Inc. and Alliant Techsystems, Inc. (“ATK”) entered into a contract under which SNC would provide engineering, procurement, and construction services for the construction of a nitric acid and sulfuric acid concentration plant at the Radford, Virginia arsenal operated by ATK. SNC claimed that ATK’s delay in choosing an appropriate acid-resistant concrete for the ground floor and ATK’s denial of SNC’s request for an extension of time for severe winter weather each damaged SNC.

ATK moved for partial summary judgment, seeking to bar, among others, SNC’s claims (1) resulting from ATK’s delay in choosing a material and (2) resulting from severe winter weather.

Structure Tone, Inc. v. Universal Services Group, Ltd.
929 N.Y.S. 2d 242 (App. Div. 2011)

This action arose out of the construction of a Whole Foods Market in the AOL/Time Warner Center at Columbus Circle in Manhattan. The general contractor, Structure Tone, Inc., (“STI”) retained Universal Service Group (“USG”) to waterproof the market. STI sued USG, claiming that the waterproofing failed on 15 occasions, causing water to leak from the Whole Foods Market into various tenant spaces below. STI undertook to remedy the problem, and as a result, allegedly sustained damages totaling $1.2 million. STI alleged causes of action for negligence and breach of contract, seeking as damages the costs of remediation, loss of profit, recovery of the amounts paid to USG and contract balances not paid by Whole Foods.

Atlantic City Associates, LLC v. Carter & Burgess Consultants, Inc., et al
2011 U.S. App. LEXIS 9191 (3rd Cir. May 4, 2011)

* Please note that the Third Circuit issued this opinion as a non precedential opinion pursuant to Third Circuit Internal Operating Procedure Rule 5.7.

Atlantic City Associates (“ACA”) hired Carter & Burgess Consultants, Inc. (“C&B”) to oversee construction of a development in Atlantic City, New Jersey. Following numerous delays, ACA sued C&B and obtained a total recovery, including attorneys’ fees, costs and interest, of nearly $13 million. On appeal, C&B argued that the District Court failed to apply several clauses of the parties’ agreement waiving consequential damages, and failed to enforce an additional clause limiting C&B’s total liability to its compensation.

Los Angeles Unified School District v. Great American Insurance Company
49 Cal. 4th 739 (July 12, 2010)

On July 12, 2010, the California Supreme Court filed a ruling significant to public entities entering into contracts for public works projects. In Los Angeles Unified School District v. Great American Insurance Company, the Court held that a public entity “may be required to provide extra compensation if it knew, but failed to disclose, material facts that would affect the contractor’s bid or performance,” even when the failure to disclose information was not fraudulent. Articulating a test modeled after the federal courts’ superior knowledge doctrine, the high court articulated four conditions that must be met for such liability to attach.

Hartford Fire Insurance Co. v. City of Mont Belvieu
2010 U.S. App. Lexis 14277 (5th Cir. July 13, 2010)

The Court of Appeals for the Fifth Circuit recently held that a Texas City’s bond claim was time barred under the statute of limitations and equitable remedies based on estoppel were unavailable to revive claims on the bond.

Hartford Fire Insurance Company issued a performance bond for a contractor constructing a public recreational facility for the City of Mont Belvieu, Texas. The bond was a requirement under Texas public work contracts. By statute, the bond was subject to a one-year limitations period commencing from project final completion. The project progressed with numerous delays and changes. However, the City issued a certificate of occupancy in mid-2001, taking possession and operating the facility by July 2002.

At that time, numerous punch list items remained and several subcontractors owed payment by contractor filed claims on a payment bond. Hartford advised the City to be cautious when releasing further payment to contractor. Thereafter, in July 2002, City paid contractor almost $675,000 as an equitable adjustment via a change order. Critically, the change order stated that the project’s completion date was July 19, 2001.