Dooley & Mack Constructors, Inc., v. Developers Surety & Indemnity Company
2007 Fla. App. LEXIS 17769 (Fla. Ct. App. Nov. 7, 2007)
Dooley & Mack Constructors, Inc. (“Contractor”), the general contractor on a Miami-Dade Community College project, was the obligee on a performance bond issued by Developers Surety and Indemnity Company (“Surety”), on behalf of Buildtec Construction Group, Inc., the masonry subcontractor (“Subcontractor”). After Subcontractor defaulted by abandoning the job, Contractor completed the masonry work itself and sued the Surety for the resulting damages.

James Corp. v. North Allegheny School District
No. 1268 C.D., 2007 Pa. Commw. LEXIS 636 (Pa. Commw. Ct. Nov. 30, 2007)
The Pennsylvania Commonwealth Court held that the “measured mile” method of proving damages for an acceleration claim was legally sufficient to establish the extent of the contractor’s damages. The Court also held the contractor’s failure to provide notice in accordance with the contract was not fatal to the claim, and that attorney fees and expenses under the Prompt Payment Act must be apportioned to those fees and expenses associated with recovering payment’s due under the contract.

Northeast Fence & Iron Works, Inc. v. Murphy Quigley Co.
933 A.2d 664, 2007 Pa. Super. LEXIS 3092 (Pa. Super. Ct. Sept. 18, 2007)
The Pennsylvania Superior Court held that a subcontractor could recover on a theory of unjust enrichment against a contractor where the subcontractor proved that it performed work for which it was not paid and that this work satisfied the contractor’s obligations to a third party. The Subcontractor was not required to prove payment to the Contractor by the Owner.

Caddell Construction Co., Inc. v. United States
2007 U.S. Claims LEXIS 285, No. 04-461C, (September 7, 2007)
The United States District Court of Federal Claims held that the design deficiencies alleged by the plaintiff contractor did not rise to the level of a breach of the implied warranty set forth under the Spearin Doctrine.
Plaintiff Caddell Construction Co. (“Plaintiff”) entered into a contract with the Department of Veteran Affairs (the “Government”) to modernize and strengthen the VA Medical center in Memphis, Tennessee. Plaintiff claimed on behalf of its steel fabrication subcontractor, Steel Service Corporation (“SSC”), that the Government provided structural steel drawings that contained conflicts, errors, omissions, and/or inadequate details which resulted in delay and additional costs to SSC.

National American Insurance Company v. United States
No. 2007-5016, 2007 U.S. App. LEXIS 20058 (Fed. Cir. August 23, 2007)
The US Court of Appeals for the Federal Circuit upheld the lower court’s grant of a motion for summary judgment. The Court held that a payment bond surety is equitably subrogated to the rights of the contractor whose debt it discharges, and thus can pursue a claim directly against the government.
The case arose out of a contract between Innovative PBX Services, Inc. (“Contractor”) and the United States Small Business Administration (the “government”) for the replacement of a telephone system at the Department of Veterans Affairs Medical Center. The Contractor subcontracted part of the work to Nortel Communications Systems, Inc. (“Subcontractor”). As required by the Miller Act, the Contractor executed payment and performance bonds in favor of the government with National American Insurance Company (“Surety”) as the surety. After completion of the contract work, the Subcontractor notified the Surety that it was owed approximately $675,000 for labor and materials that the Contractor had failed to pay for. The Subcontractor then instituted a Miller Act claim under the payment bond against the Surety, which the Surety settled. The Surety also notified the government that no addition payments should be made to the Contractor in light of the Miller Act claim and requested that all remaining contract funds be held for the Surety’s benefit. The government, however, did not follow the Surety’s request and made its final contract payment to the Contractor. As a result, the Surety filed a complaint against he government seeking damages of $280,000.

Neshaminy Constructors, Inc. v. Concrete Building Systems, Inc.
2007 U.S. Dist. LEXIS 69197, Civil Action No. 06-1489 (E.D. Pa. 2007)
The United States District Court for the Eastern District of Pennsylvania conducted a bench trial in which the primary question was whether a contract had been formed between a contractor and subcontractor in connection with a project for which the contractor submitted a bid proposal utilizing, in part, the subcontractor’s bid proposal for calculating the total price for the work. Relying on Pennsylvania common law, the Eastern District held that use of a subcontractor’s bid, by a general contractor in the submission of its own bid to the owner, in and of itself is not sufficient to create a binding contract.

Pa. Associated Builders and Contractors, Inc. v. Dep’t of Gen. Servs
2007 Pa. LEXIS 2175 (Oct. 17, 2007)
On October 17, 2007 the Pennsylvania Supreme Court ruled that a lower court decision misinterpreted the state’s Procurement Code and that the Commonwealth Department of General Services (DGS) should be allowed to use a sealed proposal process to procure construction contracts.
In April, 2005, DGS initiated the use of the request for proposal (RFP) process to award construction contracts on larger projects (exceeding $5 million). In October 2005, Associated Builders and Contractors (ABC), a trade association of contractors and subcontractors, filed suit in the Commonwealth Court to enjoin DGS from using the RFP process for construction contracts, asserting that by statute construction work could only be awarded by competitive bidding requiring an award to the lowest competitive bidder. The Commonwealth Court held that the Procurement Code does not extend the RFP process to construction contracts, and, accordingly, enjoined DGS from utilizing the competitive sealed proposal bidding/RFP process on any future construction project under its policy determination. DGS appealed the Commonwealth Court’s decision.

Central Ceilings, Inc. v. Nat’l Amusements, Inc.,
70 Mass. App. Ct. 172, 873 N.E.3d 754 (Sept. 18, 2007)
National Amusements, Inc., entered into a contract with Old Colony Construction Corporation for the construction of National’s cinema theater complex. Old Colony subsequently entered into a subcontract with the plaintiff, Central Ceilings, Inc., for a portion of the construction of the Project. Although delays made meeting the original completion date next to impossible, National stressed to Central its strong desire to have the theatre complex open for the Labor Day weekend. In response, Central made it clear to National that meeting such an aggressive completion date would require it to accelerate the work schedule. In addition, since Old Colony was experiencing cash flow problems and owed Central a substantial sum of money for work already completed, Central demanded assurances from National that it would be paid for its work before it would continue with the accelerated work on the Project. As a result, one of National’s agents orally agreed to pay Old Colony’s obligations to Central. Thereafter, Central completed its work and achieved substantial completion by August 25.

PSEG Power New York, Inc. v. Alberici Constructors, Inc.
2007 U.S. Dist. LEXIS 66767 (N.D. NY. September 7, 2007)
During the course of litigation arising out of a contract for the construction of a combined-cycle power plant between the principal contractor Alberici and PSEG, an e-discovery dispute arose around the production of email. In response to Alberici’s request for documents including email and any email attachments, PSEG produced over 211,000 pages and a disc containing email, but not the email attachments. Later it was discovered that during the process in which PSEG’s vendor downloaded the emails for production, the tie between the email and its corresponding attachments was broken, making it very difficult to determine which attachment belonged to which email. However, the raw data remained intact. Around the same time, and before the close of discovery, PSEG moved for summary judgment. The District Judge struck the motion sua sponte, stating that the motion was to be renewed after discovery had been completed and the parties had consulted with the magistrate judge.

ACE Constructors, Inc. v. U.S.
2007 U.S. App. Lexis 22309 (Fed. Cir. September 19, 2007)
The US Court of Appeals for the Federal Circuit upheld a contractor’s claim for additional compensation due to differing site conditions.
ACE Constructors, Inc. (“Contractor”) entered into a contract with the United States Army Corps of Engineers (“Government”) to build a structure designated as the Ammo Hot-Load Facility, at Biggs Army Airfield at Fort Bliss in El Paso, Texas. The project included construction of a loading area for cargo planes, various roadways, buildings, a storage pad, a loading apron, and a taxiway for airplanes. The site contained hills and other terrain that needed to be excavated, leveled, and filled. The bid solicitation materials included architectural drawings and engineering specifications prepared for the government by the engineering firm of Crawford, Murphy & Tilly, Inc., which plans were incorporated into the contract.