United States v. Int’l Fid. Ins. Co., No. 16-0472-WS-C, 2017 U.S. Dist. LEXIS 16791 (S.D. Ala. Feb. 7, 2017)

This action arose out of a payment dispute between Bay South Limited, Inc. (“Bay South”) and Stephens Construction & Concrete, Inc. (“Stephens”). Bay South entered into two subcontracts with Stephens, whereby Bay South agreed to furnish labor and materials to Stephens on two federal construction projects.  In connection therewith, International Fidelity Insurance Company (“Fidelity”) issued payment bonds (the “Bonds”) to Stephens.  Bay South filed a complaint in federal court to assert claims against the Bonds under the Miller Act (40 U.S.C. §3133), as well as other claims.  Stephens sought to compel arbitration of Bay South’s claims, pursuant to the arbitration provision in the subcontracts, which provided:

“In the event of a dispute arising between [Stephens] and [Bay South] under the Subcontract Agreement, the dispute shall be settled by arbitration in accordance with the Construction Industry Rules of the American Arbitration Association then in effect …”

Bay South argued that the 1999 Amendment to the Miller Act prohibits such claims from being arbitrated, and, in the alternative, even if these claims may be arbitrated generally, Bay South’s specific claims are not subject to arbitration because they are not within the scope of the parties’ arbitration agreement.