Stacy & Witbeck, Inc. v. San Francisco,
42 Cal. Rptr. 2d 805, 1995 Cal. App. LEXIS 658 (Cal. Ct. App. Jul. 17, 1995)

A municipal public utilities commission’s order barring a contractor from bidding on the municipality’s public works projects for five years was upheld by the California appellate court where the commission found that the contractor had knowingly submitted a greatly inflated delay and disruption claim.