Tampa D Fluor Enterprises, Inc. v. Duke Energy Florida, LLC, No. 8:19-cv-00224, 2019 BL 135007, at *1 (M.D. Fla. Apr. 16, 2019)

On April 16, 2019, a Florida federal court dismissed without prejudice Fluor Enterprises’ claim that Duke Energy wrongfully drew down a $67 million letter of credit issued in connection with Fluor’s construction of a gas-fired electrical generation facility in Citrus County, Florida.  In addition to the core breach of contract claim which suffered from several procedural issues, the court dismissed extra-contractual claims for conversion, civil theft, breach of the implied covenant of good faith and fair dealing, and violation of the Florida Deceptive and Unfair Trade Practices Act.

Continue Reading Florida Federal Court Dismisses Fluor Enterprises’ $67M Claim Against Duke Energy for Wrongful Draw Down of Credit Letter