Harakas Constr., Inc. v. Metro Gov’t of Nashville, 2018 Tenn. App. LEXIS 45 (Tenn. App. January 29, 2018)

 BK Partners LLC (“BK”) sought to build a condominium complex in Davidson County.  This required an upgrade to the existing public sewer system.  Therefore BK and the Metropolitan Government of Nashville and Davidson County (“Metro”) entered into an agreement whereby Metro agreed to contribute $200,000 to the cost of the sewer upgrade with BK responsible for the actual construction.  BK hired Harakas Construction, Inc. (“Harakas”) to upgrade the system (the “Project”).  Metro was not a party to that contract (the “Contract”).

Harakas encountered unforeseen soil conditions, which resulted in two change orders that increased the Contract amount.  Under the Contract, Metro was not required to authorize change orders; nevertheless, Metro was involved in the discussions.  Harakas performed the extra work and achieved substantial completion.  However, after a defect was discovered in the upgraded system, Metro refused to fund the Project.  When BK failed to pay Harakas, Harakas sued both Metro and BK.  Against Metro, Harakas claimed promissory estoppel and unjust enrichment.  The trial court granted Metro summary judgment based on sovereign immunity.


Continue Reading Sovereign Immunity Bars Contractor’s Claims for Unjust Enrichment and Promissory Estoppel Against City Government on Semi-Public Project

Balfour Beatty Rail, Inc. v. The Kansas City Southern Railway Company, 2016 U.S. Dist. LEXIS 39086 (N.D. Tex., March 25, 2016)

The contractor contracted with owner to install 65 miles of railroad track, for a price of $12,206,666.  The owner had engaged another contractor to grade and prepare the substrate for the railroad track, and was to furnish and deliver aggregate for track ballast and track rail material to various locations along the rail route.  The contractor’s scope included all other work.  The contractor fell behind in its work, and the owner hired additional contractors to complete a portion of its scope.  The contractor blamed the delays on the owner’s late delivery of aggregate and rail, and improper subgrade preparation under a theory of differing site conditions. It sought $4.35 million in unpaid change orders, delay damages, and penalties under Texas’ prompt payment statutes.  The owner in turn sought $2.6 million in completion costs and costs of wasted aggregate.


Continue Reading Texas District Court Rejects Rail Contractor’s Delay and Prompt Payment Claims and Awards Owner More Than $3 Million

C. Szabo Contracting, Inc. v. Lorig Construction Co., 2014 IL App (2d) 131328; 2014 Ill. App. LEXIS 699 (Sept. 29, 2014)

In May of 2006, the Illinois State Toll Highway Authority (“Highway Authority”) retained Defendant Lorig Construction Company (“Lorig”) as general contractor on a construction project for improvements to Interstate 355. The Highway Authority required that Lorig subcontract a portion of its work to a “Disadvantaged Business Enterprise” (“DBE”), and that the project be performed with union labor.


Continue Reading Illinois Court Holds Relief Available to a Sub-Subcontractor Under an Unjust Enrichment Theory for Work Requested but Not Paid for By General Contractor