Underground Utility Statute

Peoples Gas Sys. v. Posen Constr., Inc., 2018 U.S. Dist. LEXIS 106427 (M.D. Fla. June 26, 2018)

In 2009 Posen Construction, Inc. (“Posen”), a road construction contractor, entered into a general contractor agreement with the Lee County Board of County Commissioners for a lane expansion and drainage system project in east Fort Myers, Florida (the “Project”).  Peoples Gas System (“PGS”), an owner of natural gas distribution facilities throughout Florida, maintained gas pipelines underneath the Project site, which required caution when Posen worked around it.  To that end, PGS marked the pipeline with flags, paint, and installed testing stations.

However, during the course of the Project, Posen learned that at certain locations construction would be impossible unless PGS removed portions of the pipeline.  Therefore, in October 2010, Posen submitted a request to Sunshine One, a notification system whereby excavators obtain the location of underground utilities before excavation.  In November 2010, a Posen employee, Mark Santos (“Santos”) was directed to excavate at a location that PGS maintained was not properly marked for the location of the gas pipeline.  Santos struck and ruptured the pipeline and was severely injured as a result.
Continue Reading Contractor Has No Duty to Indemnify Gas Company for Settlement Paid to Injured Employee Under Florida’s Underground Facility and Safety Act