Zirkelbach Constr., Inc. v. DOWL, LLC, 2017 Mont. Lexis 591 (Mont., Sept. 26, 2017)

In interpreting a state statute which makes contractual limitations on a party’s liability unenforceable in certain instances, the Supreme Court of Montana recently upheld the validity of a contract provision in a professional services agreement between a general contractor and a designer in which the parties waived consequential damages against each other and limited the liability of the designer to $50,000.00.
Zirkelbach Constr., Inc. (“Zirkelbach”) and DOWL, LLC (“DOWL”) entered into a professional services agreement (the “Agreement”), whereby DOWL agreed to provide design work to Zirkelbach, a general contractor, for the construction of a FedEx Ground facility in Billings, Montana.  The original contract price was $122,967, but was adjusted to approximately $665,000 after the parties made several addenda to the Agreement to account for additional services.


Continue Reading Montana Supreme Court Holds That a Waiver of Consequential Damages and a Partial Limitation of Liability in a Design Contract Are Not Contrary to Montana Law

Spectro Alloys Corp. v. Fire Brick Eng’rs Co., Inc., 2014 U.S. Dist. LEXIS 140817 (D. Minn. Oct. 3, 2014)

Spectro Alloys Corporation (“Spectro”) operates a smelter, and it hired Fire Brick Engineers (“FBE”) to install refractory lining to two furnaces in Spectro’s plant.  When that refractory lining failed prematurely, Spectro sued FBE for breach of express and implied warranties and for breach of contract.  Spectro sought recovery of repair costs and profits lost while its plant was shut down for repairs.


Continue Reading U.S. District Court in Minnesota Rejects Owner’s Implied Warranty Claims Against Installation Contractor – Also Holds Recovery of Lost Profits Barred By Limitation of Damages Clause