NYU Hosps. Ctr. v. HRH Constr. LLC, 2015 U.S. Dist. LEXIS 31967 (S.D.N.Y. Mar. 12, 2015)

NYU Hospitals Center (“NYU”) hired HRH Construction LLC (“HRH”) to renovate NYU’s radiology center. HRH entered into subcontracts with various trades to complete the work. The renovation project was to proceed in several phases, and the contract between NYU and HRH called for HRH to submit monthly payment requisitions for costs and expenses incurred during the preceding month.


Continue Reading US District Court in New York Holds Owner’s Interference Bars Claim that Contractor Breached By Abandoning Project